GPC RG Tanna 2022-2023 Shutdown Planner

Please see below linked GPC RG Tanna 2022-2023 Shutdown Planner v71. The updated document will also available internally through Neptune.

Please take note of the following changes from the previously published version 69 for the Aug-22 to Mar-23 period.

  1. J Route 1 day commencing on the 17/08/2022 added
  2. CC12 Tunnel 4 days commencing on the 29/08/2022 changed 7 days commencing on the 14/11/2022
  3. Berth 3 7 days commencing on the 05/09/2022 added
  4. SL2 14 days commencing on the 05/10/2022 changed to 19 days commencing on the 05/10/2022
  5. DS2/G Route 1 day 17/10/2022 removed
  6. G Route 3 days commencing on the 25/10/2022 delayed from 05/07/2022
  7. Berth 2 6 days commencing on the 07/11/2022 added
  8. Berth 4 7 days commencing on the 21/11/2022 added
  9. DS2/G Route 1 day 29/11/2022 removed
  10. Berth 1 7 days commencing on the 09/01/2023 added
  11. Berth 3 5 days commencing on the 06/02/2023 added
  12. CC20 Tunnel 4 days commencing 06/03/2023 removed